London 2012 Games, Olympic Park

The park was developed on existing waste and industrial land.

Systech International was confirmed as a designated supplier of quantity surveying services to the London 2012 Games by the British Olympic Association (BOA).

We worked on a number of construction and infrastructure packages within the Olympic Park and Olympic Village and had a full time presence on the site for a period of 3 years leading up to the Games.

Systech Solicitors’ advised on the legal and commercial impact of tender documentation and provide bid assistance using the NEC form of contract. The large international contractor was successful and the project was supported during the construction phase by the same team.

Region UK, Europe

Country UK

Sector Construction, Civil Engineering

Service Contract Management, Planning and Scheduling, Legal

Contract NEC Option C