Birmingham New Street Station

Birmingham New Street Station was re-developed over 6 year period to allow for increased passenger capacity (170,000 passengers a day) and reduced journey times. The concourse was extended by 3.5 times and enhanced passenger and car parking facilities added. The development also included retail space along with an atrium.

Systech was appointed by one of the delivery contractors to advise on and support the agreement of the final account. We worked through the project audit process with the client to a successful conclusion, whilst robustly protecting our client’s entitlements.

Value £750m

Region UK

Country UK

Sector Rail

Service Contract Management

Go Back To Projects